Secondary control - Automatic Frequency Restoration Reserves (aFRR)
With the introduction of the balancing energy market, the aFRR market will be divided into two separate stages: balancing capacity and balancing energy tendering.
Within the scope of the balancing capacity tender market participants offer pre-qualified capacities, which they must also offer on the balancing energy market, in case the bid is accepted. In addition to the capacity offered, a bid for aFRR capacity is characterized by the capacity price. The bids submitted are ranked in ascending order according to this price (merit order list for capacity). The most favorable bids for APG are finally accepted - in accordance with the published award criteria and requirements - for the capacity reserve.
The second stage of the market is formed by intraday balancing energy tenders (balancing energy market). Here, providers can adjust the energy prices already submitted in the capacity tender or offer other pre-qualified capacities, independently of the balancing capacity tender. The submitted bids are again ranked in a merit order list according to their energy price.
The individual balancing energy bids are activated automatically - again in accordance with the published criteria - by the load frequency controller of APG, specifying a capacity setpoint with the aim of balancing the control area.
Tenders for aFRR in the APG control area
Below the most important information for potential providers of aFRR is presented. More precise and legally binding information can be found in the download section.
The tenders take place exclusively via the electronic tendering platform of APG. The documents required for participation in the tenders for aFRR can be found in the download section on the right-hand side.
See conditions for participation in the tenders for control energy.
Balancing capacity auction
Tendered volume
The aFRR balancing capacity required in the APG control area which is procured in daily tenders amounts to +/-200 MW until the 12th of Aug. 2024; and will be increased to +/-225 MW as of delivery day 13th of Aug. 2024. The dimensioning of the aFRR balancing capacity to be tendered can be changed by the control area manager if necessary.
Tendered products
aFRR is procured daily in six 4-hour blocks per day for positive and negative products:
Product name | |
SRL_00_04_POS | SRL_00_04_NEG |
SRL_04_08_POS | SRL_04_08_NEG |
SRL_08_12_POS | SRL_08_12_NEG |
SRL_12_16_POS | SRL_12_16_NEG |
SRL_16_20_POS | SRL_16_20_NEG |
SRL_20_24_POS | SRL_20_24_NEG |
Minimum and maximum bids
The minimum bid size per product is 1 MW. Bids in excess of the minimum bid can be submitted in full 1 MW increments and must not exceed the pre-qualified capacity.
Capacity tender process
The required aFRR in Austria is tendered on a daily basis (calendar days, from Monday to Sunday). The most important deadlines for a tender are summarized in the following table:
Event | Time | |
Gate Open Time | Gate Open of aFRR capacity tender for delivery day D | D-7 10:00 a.m. |
Gate Closure Time | Gate Closure of aFRR capacity tender for delivery day D | D-1 09:00 a.m. |
Publication of results | Latest time for the publication of the results of the capacity tender for delivery day D | D-1 09:30 a.m. |
The following figure also shows the sequence for an entire delivery week:
Award procedure
At the end of the bidding period the offered aFRR capacity bids are ranked according to the following criteria:
- lowest capacity price;
- if the prices for capacity are the same, the award of the contract will be based on an algorithm for reproducible randomization
Market participants, whose bids are selected, receive the quoted aFRR capacity price, i.e. a "pay-as-bid" approach is used. The energy prices submitted in the capacity tender will be carried over to the energy tender and may be adjusted (downwards and upwards) until the end of the energy tender period.
Unsuccessful tender
In the event of an unsuccessful tender, e.g. in case not enough capacity is offered, the valid bids will be accepted and a “second call” will be opened for the shortfall. If there is still a shortfall after the second tender, a further invitation to tender will be opened in a "last call". In this case, APG calls on potential suppliers to offer available power via e-mail or, if possible, via telephone. In the event that the "last call" still does not suffice to cover the shortfall, APG has the right to oblige suppliers to provide the aFRR (obligation to supply). Detailed information regarding this procedure can be found in the Tendering Conditions for aFRR (German only).
Balancing Energy Auction
Tendered products
aFRR energy products are based on a validity period of 15 minutes:
Produktname | |
SRL_0000_0015_POS | SRL_0000_0015_NEG |
SRL_0015_0030_POS | SRL_0015_0030_NEG |
SRL_0030_0045_POS | SRL_0030_0045_NEG |
SRL_0045_0100_POS | SRL_0045_0100_NEG |
SRL_0100_0115_POS | SRL_0100_0115_NEG |
... | ... |
SRL_2345_0000_POS | SRL_2345_0000_NEG |
Minimum and maximum bids
The minimum bid size per product is 1 MW. Bids in excess of the minimum bid can be submitted in full 1 MW increments and must not exceed the pre-qualified capacity.
Balancing Energy Tendering Process
The required aFRR balancing energy is put out to tender intraday (from Monday to Sunday). Bids can be submitted and adjusted from the successful completion of the capacity tender until 25 minutes before the delivery period of the respective product. The most important deadlines of the tender are summarised in the following table:
Event | Time | |
Publication of capacity tender results = Gate Open Time | Gate Open for all energy tenders for delivery day D | Latest D-1 09:30 |
Gate Closure Time | Gate Closure Time of the energy tender for each product P, starting at time T | T-25 min |
Publication of tender results | Latest time for the publication of the results of the energy tender for each product, starting at time T | T-10 min |
Award procedure
After the end of the bidding period, the offered aFRR energy bids are ranked according to the following criteria:
- lowest energy price for positive aFRR or highest energy price for negative aFRR;
- if the prices for energy are the same, the award of the contract will be based on an algorithm for reproducible randomization
Once a bid has been accepted, the provider is obliged to keep the accepted quantity available for activation at any time.
Backup procedure
If the process of energy tendering cannot be fully completed for technical reasons, all bids submitted up to that point will lose their validity. Backup energy prices are calculated for the creation of the merit order list.
The calculation of the backup energy prices for delivery day D are carried out for each provider and product based on the energy bids the provider submitted for the 14 delivery days before the Gate Closure Time of the capacity tender (D-1). The calculation steps for delivery day D are as follows:
- Sorting the bids of each provider per product
- The energy bids for delivery days D-15 to D-2 are sorted according to the energy price (ascending for positive aFRR, descending for negative aFRR) and, in case of equal prices, ascending according to the size of the energy bid.
- The capacity bids for delivery day D are sorted in ascending order by capacity price and, in the case of equality, by energy price (ascending for positive aFRR, descending for negative aFRR) and time stamp (ascending).
- Calculation of an average 1-MW-MOL
- The average price for the first MW, the second MW, etc. is calculated based on the energy prices submitted.
- This MOL must then be sorted again (ascending for positive aFRR, descending for negative aFRR).
- Calculation of the backup energy price MOL
- The backup energy prices are calculated based on the 1-MW-MOL and the quantities of the bids submitted in the capacity tenders for the relevant delivery day D.
- The backup energy price of a bid is calculated as the average value of the prices from the 1-MW-MOL corresponding to the quantities of the submitted balancing capacity bids.
Two special cases can occur regarding the calculation:
- The supplier has not submitted any valid energy prices for one or more products within the last 14 calendar days before the delivery date. As a substitute, the 1-MW-MOL for this provider is calculated as the average of the 1-MW-MOLs of all other providers.
- The quantity offered for a product in the respective capacity tender exceeds that of the last 14 delivery days and thus also the length of the 1-MW-MOL. In this case, the last backup energy price is applied for all subsequent MWs.
Frequently asked questions - FAQ
aFRR is used to restore the availability of the power bandwidth of the activated FCR. aFRR is automatically activated to relieve FCR, so that it can resume its function of balancing the system. aFRR is activated when the system is affected for longer than 30 seconds or it is assumed that the system will be affected for a period longer than 30 seconds. Prior to this, deviations in the system are only covered through FCR.
To stabilize the grid frequency using aFRR it must be possible to activate the control reserve in both directions (increased/reduced generation). Therefore a certain power range is reserved for the possible activation of aFRR.
Suppliers who have entered an obligation to provide aFRR must meet this obligation over the entire delivery period without interruption. aFRR can only be generated in plants that are in operation. The supplier decides which of his prequalified power plants are used at any given time to provide the aFRR. In any case, he has to make sure that the agreed volume can be provided in full.
A supplier who cannot meet the obligation to provide aFRR due to technical problems must inform Austrian Power Grid AG immediately by telephone and also by e-mail.
If the failure can be attributed to gross negligence or intent, Austrian Power Grid AG can obligate the supplier to pay a contractual penalty and compensation.
In the event that the contractual obligations are breached repeatedly, Austrian Power Grid AG has the right to terminate the framework agreement with the supplier.
Generation units that provide aFRR can also carry out numerous scheduled and reserve deliveries. It must, however, be ensured that the agreed aFRR range is verifiably available at all times, i.e. starting from the current operating point, a power increase or a power reduction within the agreed range and quality must be possible at any time.
For monitoring purposes, the supplier must provide Austrian Power Grid AG with time-stamped measured values for frequency, operating point and generation of the individual generation via online transmission.
The supplier must also record these values to make sure that he can subsequently provide Austrian Power Grid AG with the values that may have not been transmitted.
More detailed specifications can be found in the Prequalification Documentation for aFRR (German only).
Yes, we use both a power price and an energy price for the aFRR. The bids for energy price are ranked in a Merit Order List (MOL) which is subsequently used for the call-up of bids, starting with the cheapest bid. Suppliers will receive financial compensation for keeping power for aFRR available regardless of its actual use (power price) as well as for the energy that is actually activated (energy price).
At the end of the bidding period the bids are ranked according to prices – starting with the cheapest bids – until the total volume of aFRR put out to tender is reached. Each supplier is paid the price he offered. A list with average values of accepted bids of each time frame is published on the tendering platform in the ‘results’ section.
In the event that the number of accepted bids for aFRR power does not cover the volume put out to tender, a second tender will be opened to cover the shortfall.
If there is still a shortfall after the second invitation to tender, a further invitation to tender will be opened in a "Last Call". In this case, APG calls on potential suppliers to offer available power by e-mail or if possible, by telephone.
In the event that the volume of aFRR is still insufficient after the "Last Call", APG has the right to oblige suppliers to make available and provide the aFRR power (obligation to supply).
Ansprechpartner
Market Operations
SRL-cooperations
Austria and Germany jointly procure and activate secondary control reserve. With the help of this cooperation, the opposing activation of secondary balancing power (SRL) is avoided by carrying out imbalance netting in both countries.
PICASSO / IGCC
APG is part of the International Grid Control Cooperation (IGCC), in the course of which the opposing activation of secondary control reserves is to be avoided. From the go-live and APG's accession to the European Platform for the Activation of Secondary Control Reserves (PICASSO), this bilateral cooperation will be extended to the European level.