Offer phase
Section 23b(2) EIWOG 2010 requires APG to conduct a two-stage tender procedure for the selection of grid reserve providers.
In the first part of the process, APG checked the details and evidence submitted by the providers in their expressions of interest to see if they provided the required information and meet the eligibility conditions under Section 23b(1), (2) and (4) EIWOG 2010 in addition to the technical requirements (mandatory minimum requirements).
All operators of eligible plants will be asked to submit offers within four weeks in accordance with Section 23b(3) EIWOG 2010.
The offer phase is open from 10.04.2024 to 08.05.2024 24:00 o'clock.
Contact
Netzreserve
Grid reserve
The grid reserve is intended to ensure that sufficient generation or consumption capacities are available at all times to eliminate bottlenecks in the transmission grid.